Ivanhoe Construction Co. uses the percentage-of-completion method. In 2018, Ivanhoe began work on a contract for $21000000; it was completed in 2019. The following cost
Ivanhoe Construction Co. uses the percentage-of-completion method. In 2018, Ivanhoe began work on a contract for $21000000; it was completed in 2019. The following cost data pertain to this contract:
Cost incurred during the year 2018-$6600000 and 2019-$5500000
Estimated costs to complete at the end of year 2018-5100000
The amount of gross profit to be recognized on the income statement for the year ended December 31, 2019 is
$3653846.
$3800000.
$4053846.
$8900000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started