Question

1 Approved Answer

Ivanhoe Construction entered into a contract to construct a bridge for a contract price of $2.80 million. Construction began in 2019 and was completed in

Ivanhoe Construction entered into a contract to construct a bridge for a contract price of $2.80 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract:

2019 2020 2021
Costs incurred during the year $653,000 $806,000 $709,900
Estimated costs to complete 1,436,600 541,000 0

Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places, e.g. 52.75% and other answers to 0 decimal places, e.g. 1,525.)

2019 2020 2021
Revenue $

$

$

Expenses

Gross Profit $

$

$

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Using Financial Accounting Information The Alternative to Debits and Credits

Authors: Gary A. Porter, Curtis L. Norton

7th Edition

978-0-538-4527, 0-538-45274-9, 978-1133161646

Students also viewed these Accounting questions