I've Tried my hardest to understand this and i can't i need help. And online school doesn't help. Construct a PERT/CPM chart based on the

I've Tried my hardest to understand this and i can't i need help. And online school doesn't help.

Construct a PERT/CPM chart based on the table below. Determine the critical path.

Use the "Most Likely Time" as the duration for each activity.Ignore the "Most Optimistic Time" and the "Most Pessimistic Time".

image text in transcribed
Time -Estimates (in weeks) Activity . Preceding Most optimistic Most likely Most Pessimestic activity time (a) time (m) time (b) None NJ 12 None 26 BC 9 D 3.5 E, F,G

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions