Jacob is under pressure from the sponsor to finish the project on time. While creating the schedule, he has identified that a certain activity can
Jacob is under pressure from the sponsor to finish the project on time. While creating the schedule, he has identified that a certain activity can be delayed without delaying the early start date of subsequent activities. What best describes what Jacob is doing