Answered step by step
Verified Expert Solution
Question
00
1 Approved Answer
Jadin Davis Chapter 2 6 . Ch 2 6 - 9 Build a Model Bradford Services Inc. ( BSI ) is considering a project that
Jadin Davis Chapter Ch Build a Model Bradford Services Inc. BSI is considering a project that has a cost of $ million and an expected life of years. There is a percent probability of good conditions, in which case the project will provide a cash flow of $ million at the end of each year for years. There is a percent probability of medium conditions, in which case the annual cash flows will be $ million, and there is a percent probability of bad conditions and a cash flow of $ million per year. BSI uses a percent cost of capital to evaluate projects like this. a Find the project's expected cash flows and NPV WACC Condition Probability CF CF x Prob. Good $ $ Medium $ $ Bad $$ Expected CF $ Time line of Expected CF $ $ $ $ NPV$ Without any real options, reject the project. It has a negative NPV and is quite risky. b Now suppose the BSI can abandon the project at the end of the first year by selling it for $ million. BSI will still receive the Year cash flows, but will receive no cash flows in subsequent years. Assume the salvage value is risky and should be discounted at the WACC. WACC Salvage Value $ Riskfree rate Discounted $ Decision Tree Analysis Cost Future Cash Flows NPV this Probability Probability Scenario x NPV $ $ $ $ $ $ $ $ $ $ Expected NPV of Future CFs When abandonment is factored in the very large negative NPV under bad conditions is reduced, and the expected NPV becomes positive. Note that even though the NPV of medium is still negative, it is higher than it would be if the project was abandoned at year if conditions are medium. d Now suppose the original no abandonment and no additional growth project could be delayed a year. All the cash flows would remain unchanged, but information obtained during that year would tell the company exactly which set of demand conditions existed. Use decision tree analysis to estimate the value of the project if it is delayed by year. Hint: Discount the $ million cost at the riskfree rate since it is known with certainty. Show two time lines, one for operating cash flows and one for the cost, then sum their NPVs WACC Riskfree rate Decision Tree Analysis: Optg. CFs "Future Operating Cash Flows Discount at WACC NPV this Probability Probability Scenario x NPV $ $ $ Expected PV of Future CFs Decision Tree Analysis: Costs "Future Cost of Implementation Discount at RiskFree Rate Cost NPV this Probability Probability Scenario x NPV Expected PV of Future CFs "Total NPV NPV of Future Operating CF plus NPV of Future Year cost of implenting additional project Since the NPV from waiting is positive and the NPV from immediate implementation is negative, it makes sense to delay the decision for a year.
Jadin Davis
Chapter Ch Build a Model
Bradford Services Inc. BSI is considering a project that has a cost of $ million and an expected life of years. There is a percent probability of good conditions, in which case the project will provide a cash flow of $ million at the end of each year for years. There is a percent probability of medium conditions, in which case the annual cash flows will be $ million, and there is a percent probability of bad conditions and a cash flow of $ million per year. BSI uses a percent cost of capital to evaluate projects like this.
a Find the project's expected cash flows and NPV
WACC
Condition Probability CF CF x Prob.
Good $ $
Medium $ $
Bad $$
Expected CF $
Time line of Expected CF
$ $ $ $
NPV$
Without any real options, reject the project. It has a negative NPV and is quite risky.
b Now suppose the BSI can abandon the project at the end of the first year by selling it for $ million. BSI will still receive the Year cash flows, but will receive no cash flows in subsequent years. Assume the salvage value is risky and should be discounted at the WACC.
WACC Salvage Value $
Riskfree rate Discounted $
Decision Tree Analysis
Cost Future Cash Flows NPV this Probability
Probability Scenario x NPV
$ $ $
$ $ $ $
$ $ $
Expected NPV of Future CFs
When abandonment is factored in the very large negative NPV under bad conditions is reduced, and the expected NPV becomes positive. Note that even though the NPV of medium is still negative, it is higher than it would be if the project was abandoned at year if conditions are medium.
d Now suppose the original no abandonment and no additional growth project could be delayed a year. All the cash flows would remain unchanged, but information obtained during that year would tell the company exactly which set of demand conditions existed. Use decision tree analysis to estimate the value of the project if it is delayed by year. Hint: Discount the $ million cost at the riskfree rate since it is known with certainty. Show two time lines, one for operating cash flows and one for the cost, then sum their NPVs
WACC
Riskfree rate
Decision Tree Analysis: Optg. CFs "Future Operating Cash Flows
Discount at WACC
NPV this Probability
Probability Scenario x NPV
$
$
$
Expected PV of Future CFs
Decision Tree Analysis: Costs "Future Cost of Implementation
Discount at RiskFree Rate
Cost NPV this Probability
Probability Scenario x NPV
Expected PV of Future CFs
"Total NPV NPV of Future Operating CF plus
NPV of Future Year cost of implenting additional project
Since the NPV from waiting is positive and the NPV from immediate implementation is negative, it makes sense to delay the decision for a year.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started