Jalbert Incorporated planned to use materials of $8 per unit but actually used materials of $14 per unit, and planned to make 1,510 units but
Jalbert Incorporated planned to use materials of $8 per unit but actually used materials of $14 per unit, and planned to make 1,510 units but actually made 1,790 units. The flexible - budget amount for materials is A. $21,140 B. $12,080 C. $14,320 D. $25,060