Jalbert Incorporated planned to use materials of $9 per unit but actually used materials of $13 per unit, and planned to make 1,530 units
Jalbert Incorporated planned to use materials of $9 per unit but actually used materials of $13 per unit, and planned to make 1,530 units but actually made 1.750 units. The flexible-budget variance for materials is OA. $7,000 favorable OB. $7,000 unfavorable OC. $6,120 favorable OD. $6,120 unfavorable