Question: Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of $1500 per section. Her

  • Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of $1500 per section.
  • Her plan was to complete 2 sections in week one.
  • You, as the PM, check the financials at the end of week one and you see that Jane has spent $1800 and has completed 1 section.
  • How is Jane doing on this project as determined by Earned Value analysis?

Calculate the following:

  • PV =?
  • AC =?
  • EV =?
  • CV =?
  • SV =?
  • CPI =?
  • SPI =?
  • BAC =?
  • EAC =?
  • VAC =?
  • ETC =?
  • TCPI =?

Step by Step Solution

3.46 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

PV 33 9000 3000 AC 1800 EV 166690001500 CV 15001800 300 SV 15003000 150... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

6079507126bd3_70930.docx

120 KBs Word File

Students Have Also Explored These Related Finance Questions!