Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of $1500 per section. Her
- Jane has a fence to complete in 4 weeks. The fence will have six sections and she has a budget of $1500 per section.
- Her plan was to complete 2 sections in week one.
- You, as the PM, check the financials at the end of week one and you see that Jane has spent $1800 and has completed 1 section.
- How is Jane doing on this project as determined by Earned Value analysis?
Calculate the following:
- PV =?
- AC =?
- EV =?
- CV =?
- SV =?
- CPI =?
- SPI =?
- BAC =?
- EAC =?
- VAC =?
- ETC =?
- TCPI =?
Step by Step Solution
★★★★★
3.46 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
PV 33 9000 3000 AC 1800 EV 166690001500 CV 15001800 300 SV 15003000 150...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 1 attachment)
6079507126bd3_70930.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started