XYZ Company has experienced increased production costs. The primary area of concern identified by management is direct labor. The company is considering adopting a standard
XYZ Company has experienced increased production costs. The primary area of concern identified by management is direct labor. The company is considering adopting a standard cost system to help control labor and other costs. Useful historical data are not available because detailed production records have not been maintained.
To establish labor standards, XYZ Company has retained an engineering consulting firm. After a complete study of the work process, the consultants recommended a labor standard of one unit of production every 30 minutes, or 16 units per day for each worker. The consultants further advised that XYZ’s wage rates were below the prevailing rate of $15 per hour.
XYZ’s production vice-president thought that this labor standard was too tight, and from experience with the labor force, believed that a labor standard of 40 minutes per unit or 12 units per day for each worker would be more reasonable.
The president of XYZ Company believed the standard should be set at a high level to motivate the workers and to provide adequate information for control and reasonable cost comparison. After much discussion, management decided to use a dual standard. The labor standard of one unit every 30 minutes, recommended by the consulting firm, would be employed in the plant as a motivation device, while a cost standard of 40 minutes per unit would be used in reporting.
Management also concluded that the workers would not be informed of the cost standard used for reporting purposes. The production vice-president conducted several sessions prior to implementation in the plant, informing the workers of the new standard cost system and answering questions. The new standards introduced when wages were increased to the standard direct labor rate of $14 per hour.
The standard cost system was implemented on January 1, 2018. At the end of six months of operation, actual production and direct labor hours are:
January February March April May June
Production (units) 5,100 5,000 4,700 4,500 4,300 4,400 Direct labor hours 3,000 2,900 2,900 3,000 3,000 3,100 Quantity Variances: Variance based on labor standard (one unit each 30 minutes) Variance based on cost standard (one unit each 40 minutes)
jan | feb | march | april | may | june | |
production units | 5100 | 5000 | 4700 | 4500 | 4300 | 4400 |
direct laor hours | 3000 | 2900 | 2900 | 3000 | 3000 | 3100 |
quantity variances: | ||||||
one unit each 30 min | ||||||
one unit each 40 min |
*U = Unfavorable; F = Favorable
Actual direct labor rate approximated the standard rate, and materials quality, labor mix, and plant facilities and conditions have not changed to any great extent during the six month period.
Required:
1 Compute the Direct Labor Quantity variances for each month, under both the motivational and reporting standards.
2 Discuss the impact of different types of standards on employee motivation. Specifically, discuss your opinion of the likely effect on motivation of adopting the labor standard recommended for XYZ Company by the engineering firm.
3 Evaluate XYZ Company’s decision to employ dual standards in its standard cost system.
Step by Step Solution
3.37 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
A direct labor variance is caused by differences in either wage rates or hours worked As with direct materials variances you can use either formulas or a diagram to compute direct labor variances Util...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started