Question

1 Approved Answer

JASPEN Development Sdn Bhd expert in construction of shoplots and shopping malls. The marketing manager identified a RM5,000 million project on development of a new

JASPEN Development Sdn Bhd expert in construction of shoplots and shopping malls. The marketing manager identified a RM5,000 million project on development of a new shopping mall in Batu Kawan, Penang.The data related to the new shopping mall project is as follows:

Direct materials required:

(i)1,000,000 pieces of alluminium bar type G is required to be used in the project.The original cost of alluminium bar type G was RM80 per piece but as the bar has not been required for the last two years, it has been written down to RM25 per piece scrap value. The only foreseeable alternative use is as a substitute for alluminium bar type H (in current use) but this would involve further processing costs of RM15 per piece. The current cost of alluminium bar type H is RM55 per piece.

(ii)Other materials cost is RM1,210 millions.

Site workers required:

Total estimated site worker hours involve in this project is 54million hours. One third of the total labour hours is skilled worker and the rest is semi-skilled worker hours. A worker possessing the necessary skills is currently paid RM30 per hour. A replacement would, however, have to be obtained at a rate of RM24 per hour for the work which would otherwise be done by the skilled workers. The current rate for semi-skilled work is RM11 per hour andadditional workers could be appointed for this work.

The other project costs are listed as below:

RM'million

Contractors2,200

Legal Costs250

Costs payable to local authorities100

Required:

(a)Determine the project net profit. Show all workings clearly.

(11 marks)

(b)Based on the project contract, the timing expected receipt and payments proportion are listed as below:

Beginning of year

20222023202420252026

Contract value10%20%65%5%

Direct Materials30%30%40%

Site Workers25%25%25%25%

Contractors' Progress30%30%20%15%5%

Legal Cost100%

Cost payable to

Local authorities50%50%

Prepare the Yearly Cash Budget of the project. Show all workings clearly.

(19 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Comprehensive Assurance & Systems Tool An Integrated Practice Set

Authors: Laura R Ingraham, J Greg Jenkins

3rd Edition

0133251969, 9780133251968

More Books

Students also viewed these Accounting questions

Question

Is iced water a pure substance? Why?

Answered: 1 week ago