Jasper Company, a machine tooling firm, has several plants. One plant, located in Saint Cloud, Minnesota, uses a job order costing system for its batch

Jasper Company, a machine tooling firm, has several plants. One plant, located in Saint Cloud, Minnesota, uses a job order costing system for its batch production processes. The Saint Cloud plant has two departments through which most jobs pass. Plantwide overhead, which includes the plant managers salary, accounting personnel, cafeteria, and human resources, is budgeted at $200,000. During the past year, actual plantwide overhead was $183,000. Each departments overhead consists primarily of depreciation and other machine-related expenses. Selected budgeted and actual data from the Saint Cloud plant for the past year are as follows:
Department A Department B
Budgeted department overhead (excludes plantwide overhead) $ 120,000 $ 308,000
Actual department overhead 125,000323,000
Expected total activity:
Direct labor hours 38,00010,000
Machine-hours 15,00044,000
Actual activity:
Direct labor hours 40,0008,600
Machine-hours 15,50046,000
For the coming year, the accountants at the Saint Cloud plant are in the process of helping the salesforce create bids for several jobs. Projected data pertaining only to job number 110 are as follows:
Direct materials $ 17,000
Direct labor cost:
Department A (2,200 hours)33,000
Department B (500 hours)11,000
Machine-hours projected:
Department A 150
Department B 1,200
Units produced 11,000
c-1. The sales policy at the Saint Cloud plant dictates that job bids be calculated by adding 26 percent to total manufacturing costs. What would be the bid for job number 110 using an overhead rate of $13.08 per direct labor hour?
c-2. The sales policy at the Saint Cloud plant dictates that job bids be calculated by adding 26 percent to total manufacturing costs. What would be the bid for job number 110 using the following three separate overhead rates based on machine hours?
Plantwide rate of $3.39 per machine hour
Department A overhead rate of $8.00 per machine hour
Department B overhead rate of $7.00 per machine hour
c-3. Which of the overhead allocation methods would you recommend?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting The Basics

Authors: Ilias Basioudis

1st Edition

1138605514, 9781138605510

More Books

Students also viewed these Accounting questions