Question
Jasper Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per
Jasper Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: |
Days | |
Wait time | 17.4 |
Inspection time | 0.2 |
Process time | 2.20 |
Move time | 0.2 |
Queue time | 3.5 |
Required: | |
a. | Compute the throughput time.(Round your answer to 2 decimal places.) |
Throughput time | days |
b. | Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your final answer to 2 decimal places.) |
MCE |
c. | What percentage of the production time is spent in non-value-added activities? (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the "%" sign in your response.) |
Percentage of the production time | % |
d. | Compute the delivery cycle time. (Round your answer to 1 decimal place.) |
Delivery cycle time | days |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started