Jean is managing a project in his organization. The planned value for this project is $4,500. At the end of eight weeks, he finds that
Jean is managing a project in his organization. The planned value for this project is $4,500. At the end of eight weeks, he finds that his earned value is $3,500. What is the present schedule variance for the project? What does the variance signify? Group of answer choices $-1,000; behind schedule $+1,000; ahead of schedule $-1,000; on schedule $+1,000; on schedule $+1,000; behind schedule