Jennifer Bellin has been put in charge of planning her company's annual leadership conference. The dates of the conference have been determined by her company's
Jennifer Bellin has been put in charge of planning her company's annual leadership conference. The dates of the conference have been determined by her company's executive team. The accompanying table contains information about the activities, predecessors, and activity times (in days). Develop a spreadsheet model for finding the project completion time and critical path.
Activity Time Activity Predecessors (days) A Develop conference 3 theme B Determine attendees 3 C Contract facility A D Choose entertainment A 10 E Send announcement B 5 F Order gifts B 5 Order materials B H Plan schedule of C 40 sessions Design printed B. H 15 materials J Schedule session C rooms K Print directions L Develop travel memo M Write gift letter N Confirm catering FIITMI O Communicate with speakers P Track RSVPs and 30 assign roommates Q Print materials R Assign table numbers 07 - S Compile packets of materials T Submit audiovisual O needs U Put together welcome P 5 letter V Confirm arrangements P 3 with hotel W Print badges G. P 5Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started