Question
Jets Ltd. contracted to build a high-rise for $ 6,000,000. Construction began in 2020 and is expected to be completed in 2020. Data for 2020
Jets Ltd. contracted to build a high-rise for $ 6,000,000. Construction began in 2020 and is expected to be completed in 2020. Data for 2020 and 2021 are:
20202021
Costs incurred................................................................. $ 900,000$ 1,700,000
Estimated costs to complete........................................... 3,600,0002,400,000
Instructions
Using the percentage-of-completion method and the cost-to-cost basis,
a)How much gross profit should be reported for 2020? Show your calculation.
b)How much gross profit should be reported for 2021? Show your calculation.
c)Prepare the journal entry to record the revenue and gross profit for 2021.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started