Question

1 Approved Answer

JJ Construction Inc. entered into a contract with a customer to build a movable storage facility on January 1, 2020, for $2,100,000. JJ Construction Inc.

JJ Construction Inc. entered into a contract with a customer to build a movable storage facility on January 1, 2020, for $2,100,000. JJ Construction Inc. owns the work in process and constructs this type of storage unit for a number of customers. The customer made a down payment of 10% of the project, with an additional 10% due at the end of year one and the remaining due when it takes control of the facility. The facility is expected to be completed in two years for a total cost of $1,680,000. Actual costs incurred through December 31, 2020, are $700,000. Determine the amount of revenue to record in 2020.

Revenue to recognize in 2020

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Value Added Auditing CERM Academy Series On Enterprise Risk Management

Authors: Greg Hutchins

4th Edition

978-0965466554

More Books

Students also viewed these Accounting questions