JME is considering the difference between W/A and FIFO when it comes to process costing. Below is some data from a previous month. Beginning WIP
JME is considering the difference between W/A and FIFO when it comes to process costing. Below is some data from a previous month.
Beginning WIP 1,000 units
RM >> 60% complete >> $1,200
C >> 35% complete >> $1,750
Started 42,000 units
RM = $88,704
C = $181,331
Ending WIP 800 units
RM >> 80% complete >> $???
C >> 40% complete >> $???
Requirements:
1 You are to compute CGM and Ending WIP under W/A
2 - You are to compute CGM and Ending WIP under FIFO
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started