Job 401 had the following components: Amount Unit Direct Materials 90.0 lbs Direct Labour 15.0 hours The company allocates overhead based off of direct labour
Job 401 had the following components:
Amount Unit
Direct Materials 90.0 lbs
Direct Labour 15.0 hours
The company allocates overhead based off of direct labour hours. The estimated overhead for the year was $2,500,000 and direct labour allocation base of 200,000 direct labour hours. Materials costs $9 per pound (lb) and the wage rate is $22 per hour.
What is the total cost of Job 401?
$1,233.75
$997.50
$1.327.50
$1,140
Please post full solutions. Thank you
Job 401 had the following components: The company allocates overhead based off of direct labour hours. The estimated overhead for the year was $2,500,000 and direct labour allocation base of 200,000 direct labour hours. Materials costs $9 per pound (lb) and the wage rate is $22 per hour. What is the total cost of Job 401 ? $1,233.75$997.50$1.327.50$1,140Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started