Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 2,418 Direct labor-hours 74 labor-hours Direct

Job 910 was recently completed. The following data have been recorded on its job cost sheet:

Direct materials $ 2,418
Direct labor-hours 74 labor-hours
Direct labor wage rate $ 13 per labor-hour
Machine-hours 137 machine-hours

The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be:

Multiple Choice

  • $5,298

  • $2,622

  • $6,138

  • $3,380

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Mathematics

Authors: OpenStax

1st Edition

1711470554, 978-1711470559

Students also viewed these Accounting questions

Question

3 > O Actual direct-labour hours Standard direct-labour hours...

Answered: 1 week ago