Job Cost Sheet Consulting an estimate of $ 1 8 , 0 4 4 to carpet the consulting firm's newly leased office. The estimate was

Job Cost Sheet Consulting an estimate of $18,044 to carpet the consulting firm's newly leased office. The estimate was based on the following data:
Estimated direct materials:
400 meters at $32 per meter
$12,800
Estimated direct labor:
30 hours at $20 per hour
600
Estimated factory overhead (80% of direct labor cost)
480
Total estimated costs
$13,880
Markup (30% of production costs)
4,164
Total estimate
$18,044
On May 10, Lunden Consulting signed a purchase contract, and the carpet was delivered and installed on May 15.
The related materials requisitions and time tickets are summarized as follows:
\table[[Materials Requisition No.,Description,Amount],[132,360 meters at $32,$11,520
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Accounting A Decision Emphasis

Authors: Germain B. Boer, William L. Ferrara, Debra C. Jeter

4th Edition

0873939123, 978-0873939126

More Books

Students also viewed these Accounting questions

Question

How does a CPU increase the speed of the system clock?

Answered: 1 week ago