Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a

Job Cost Sheet

Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons for the variances between the estimated and actual costs are noted on the sheet. The data are then available to management in evaluating the efficiency of operations and in preparing quotes on future jobs. On October 1, Remnant Carpet Company gave Jackson Consulting an estimate of $2,418 to carpet the consulting firms newly leased office. The estimate was based on the following data:

Estimated direct materials:
30 meters at $34 per meter $ 1,020
Estimated direct labor:
16 hours at $30 per hour 480
Estimated factory overhead (75% of direct labor cost) 360
Total estimated costs $1,860
Markup (30% of production costs) 558
Total estimate $2,418

On October 3, Jackson Consulting signed a purchase contract, and the delivery and installation were completed on October 10.

The related materials requisitions and time tickets are summarized as follows:

Materials Requisition No. Description Amount
112 15 meters at $34 $510
114 19 meters at $34 646
Time Ticket No. Description Amount
H10 8 hours at $30 $240
H11 12 hours at $30 360

Required:

Enter amounts as positive numbers.

1. Complete that portion of the job order cost sheet that would be prepared when the estimate is given to the customer.

2. Record the costs incurred, and complete the job order cost sheet.

JOB ORDER COST SHEET
Customer Jackson Consulting Date October 1
Date wanted October 10
Date completed October 10
Job. No.
ESTIMATE
Direct Materials Direct Labor Summary
Amount Amount Amount
30 Meters at $34 $______ 16 Hours at $30 $____ Direct Materials $_______
Direct Labor ________
Factory Overhead ________
Total $_______ Total $______ Total cost $________
ACTUAL
Direct Materials Direct Labor Summary
Mat. Req. No. Description Amount Time Ticket No. Description Amount Item Amount
112 15 Meters at $34 $_______ H10 8 Hours at $30 $_____ Direct Materials $_____
Direct Labor _____
114 19 Meters at $34 ______ H11 12 Hours at $30 ______ Factory Overhead ________
Total $____ Total $_____ Total Cost $_____

What is the best explanation for the variances between actual costs and estimated costs. (For this purpose, assume that the additional meters of material used in the job were spoiled, the factory overhead rate has proven to be satisfactory, and an inexperienced employee performed the work.)

  1. The direct materials cost exceeded the estimate by $136 because 4 meters of materials were spoiled. The direct labor cost exceeded the estimate by $120 because an additional 4 hours of labor were used by an inexperienced employee. The factory overhead cost exceeded the estimate because an additional $90 of factory overhead was allocated because of the increase in direct labor.
  2. Management didn't provide enough direction to complete tasks on budget.
  3. The direct materials cost exceeded the estimate by $75 because 3 meters of materials were spoiled.
  4. The direct labor cost exceeded the estimate by $120 because an additional 4 hours of labor were used by an inexperienced employee.

Select the correct answer from the above choices. a, b, c, d

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Auditing

Authors: Hall, J Scott Harr

3rd Edition

1133008046, 978-1439079119

More Books

Students also viewed these Accounting questions

Question

What personality characteristics relate to personality disorders?

Answered: 1 week ago