Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79

Job Costs, Ending Work in Process

During March, Aragon Company worked on three jobs. Data relating to these three jobs follow:

Job 78 Job 79 Job 80
Units in each order 270 250 330
Units sold 250
Materials requisitioned $1,620 $1,300 $3,729
Direct labor hours 297 275 528
Direct labor cost $2,970 $3,575 $4,224

Overhead is assigned on the basis of direct labor hours at a rate of $7.60 per direct labor hour. During March, Jobs 78 and 79 were completed and transferred to Finished Goods Inventory. Job 79 was sold by the end of the month. Job 80 was the only unfinished job at the end of the month.

Required:

1. Calculate the per-unit cost of Jobs 78 and 79. Round your answers to the nearest cent.

Job 78 $ per unit
Job 79 $ per unit

2. Compute the ending balance in the work-in-process inventory account. Round your answer to the nearest cent.

$

3. Prepare the journal entries reflecting the completion of Jobs 78 and 79 and the sale of Job 79. The selling price is 140 percent of cost. Round your answers to the nearest cent.

Completion of Jobs 78 & 79
Sale of Job 79 (cost)
Sale of Job 79 (sale)

Options for problem 3: Completion of Jobs and Sale of Job 79

  • Accounts Receivable
  • Cash
  • Cost of Goods Sold
  • Finished Goods
  • Sales Revenue
  • Work in Process

Options for Sale of Job 79image text in transcribed

  • Accounts Receivable or Cash
  • Cost of Goods Sold
  • Finished Goods
  • Sales Revenue
  • Work in Process
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79 Job 80 Units in each order 270 250 330 Units sold 250 Materials requisitioned $1,620 $1,300 $3,729 Direct labor hours 297 275 528 Direct labor cost $2,970 $3,575 $4,224 Overhead is assigned on the basis of direct labor hours at a rate of $7.60 per direct labor hour. During March, Jobs 78 and 79 were completed and transferred to Finished Goods Inventory. Job 79 was sold by the end of the month. Job 80 was the only unfinished job at the end of the month. Required: 1. Calculate the per-unit cost of Jobs 78 and 79. Round your answers to the nearest cent. per unit Job 78 Job 79 $0 $ per unit 2. Compute the ending balance in the work-in-process inventory account. Round your answer to the nearest cent. 3. Prepare the journal entries reflecting the completion of Jobs 78 and 79 and the sale of Job 79. The selling price is 140 percent of cost. Round your answers to the nearest cent. Completion of Jobs 78 & 79 Sale of Job 79 (cost) Sale of Job 79 (sale)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foundations of Financial Management

Authors: Stanley Block, Geoffrey Hirt, Bartley Danielsen

16th edition

978-1259277160

Students also viewed these Accounting questions