Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow: Job 78 Job 79

Job Costs, Ending Work in Process

During March, Aragon Company worked on three jobs. Data relating to these three jobs follow:

Job 78 Job 79 Job 80
Units in each order 260 160 230
Units sold 160
Materials requisitioned $1,924 $816 $2,300
Direct labor hours 286 176 391
Direct labor cost $3,146 $2,816 $3,754

Overhead is assigned on the basis of direct labor hours at a rate of $8.60 per direct labor hour. During March, Jobs 78 and 79 were completed and transferred to Finished Goods Inventory. Job 79 was sold by the end of the month. Job 80 was the only unfinished job at the end of the month.

Required:

1. Calculate the per-unit cost of Jobs 78 and 79. Round your answers to the nearest cent.

Job 78 per unit
Job 79 per unit

2. Compute the ending balance in the work-in-process inventory account. Round your answer to the nearest cent.

3. Prepare the journal entries reflecting the completion of Jobs 78 and 79 and the sale of Job 79. The selling price is 140 percent of cost. Round your answers to the nearest cent.

Completion of Jobs 78 & 79 fill in the blank
fill in the blank
Sale of Job 79 (cost) fill in the blank
fill in the blank
Sale of Job 79 (sale) fill in the blank
fill in the blank

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions