Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When

Job Order Cost Sheet

Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons for the variances between the estimated and actual costs are noted on the sheet. The data are then available to management in evaluating the efficiency of operations and in preparing quotes on future jobs. On October 1, Remnant Carpet Company gave Jackson Consulting an estimate of $2,240 to carpet the consulting firms newly leased office. The estimate was based on the following data:

Estimated direct materials:
30 sq. ft. at $30 per sq. ft. $900
Estimated direct labor:
20 hours at $20 per hour 400
Estimated factory overhead (75% of direct labor cost) 300
Total estimated costs $1,600
Markup (40% of production costs) 640
Total estimate $2,240

On October 3, Jackson Consulting signed a purchase contract, and the delivery and installation was completed on October 10.

The related materials requisitions and time tickets are summarized as follows:

Materials Requisition No. Description Amount
112 15 sq. ft. at $30 $450
114 19 sq. ft. at $30 570
Time Ticket No. Description Amount
H10 10 hours at $20 $200
H11 14 hours at $20 280

Required:

Question Content Area

Enter amounts as positive numbers.

1. Complete that portion of the job order cost sheet that would be prepared when the estimate is given to the customer.

2. Record the costs incurred and complete the job order cost sheet.

JOB ORDER COST SHEET
Customer Jackson Consulting Date October 1
Date wanted October 10
Date completed October 10
Job. No.
ESTIMATE
Direct Materials Direct Labor Summary
Amount Amount Amount
30 sq. ft. at $30 20 Hours at $20 Direct Materials
Direct Labor
Factory Overhead
Total Total Total cost
ACTUAL
Direct Materials Direct Labor Summary
Mat. Req. No. Description Amount Time Ticket No. Description Amount Item Amount
310 15 sq. ft. at $30 H10 10 Hours at $20 Direct Materials
Direct Labor
312 19 sq. ft. at $30 H11 14 Hours at $20 Factory Overhead
Total Total Total Cost

Question Content Area

What is the best explanation for the variances between actual costs and estimated costs? (For this purpose, assume that the additional square feet of material used in the job were spoiled, the factory overhead rate has been proved to be satisfactory, and an inexperienced employee performed the work.)

  1. The direct materials cost exceeded the estimate by $120 because 4 square feet of materials were spoiled. The direct labor cost exceeded the estimate by $80 because an additional 4 hours of labor were used by an inexperienced employee. The factory overhead cost exceeded the estimate because an additional $60 of factory overhead was allocated because of the increase in direct labor.
  2. Management didn't provide enough direction to complete tasks on budget.
  3. The direct materials cost exceeded the estimate by $90 because 3 square feet of materials were spoiled.
  4. The direct labor cost exceeded the estimate by $240 because an additional 4 hours of labor were used by an inexperienced employee.

Select the correct answer from the above choices.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

For Heintz/parrys College Accounting, Chapters 1-15, 22nd Edition, [instant Access]

Authors: James A. Heintz, Robert W. Parry

22nd Edition

1305669886, 9781305669888

More Books

Students also viewed these Accounting questions