job was budgeted to require 5 hours of labor per unit at $9.00 per hour. The job consisted of 6,000 units and was completed in

job was budgeted to require 5 hours of labor per unit at $9.00 per hour. The job consisted of 6,000 units and was completed in 27,000 hours at a total labor cost of $274,800. What is the direct labor efficiency variance? Multiple Choice $31,800 unfavorable. $4,800 unfavorable. $27.000 unfavorable. $27,000 favorable. $31,800 favorable.

(please answer quickly i have a time limit)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions