Job X had a beginning balance of $400. During the month, direct materials of $600 and direct labour of $500 were added to the job.
Job X had a beginning balance of $400. During the month, direct materials of $600 and direct labour of $500 were added to the job. Overhead is applied to production at a rate of 30% of direct material cost. There are 5 units in Job X after the job was completed at the end of the month. What is the unit cost for Job X ? $330 $256 $220 $336