Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work
Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already at X's required resource, the scheduler schedules X to be begun immediately and assumes that X will be done four days from now. This is an example of: Group of answer choices infinite scheduling. finite scheduling. forward scheduling. backward scheduling. prioritization