Jobs A, B, and C are in queue at work center 10 before being completed on work center 20. The following information pertains to the
Jobs A, B, and C are in queue at work center 10 before being completed on work center 20. The following information pertains to the jobs and the work centers. For this problem, there is no move time. Today is day 1. If the jobs are scheduled by the earliest due date, can they be completed on time? (1) If the jobs are scheduled by the shortest process time rule, can they be completed on time? (2) What is the total idle time on work center 1 and 2, for both scheduling, respectively?
Job A C B Job Process Time (days) Due Date Work Center 10 Work Center 20 A 7 3 12 B 5 2 24 9 4 18 Work Center 10 Start Day Work Center 20 Stop Day Start Day Stop Day
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To solve this problem well schedule the jobs using both the Earliest Due Date EDD and Shortest Proce...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started