Jobs Duration (months) Predecessors Early Start (ES) Late Start (LS) Early Finish (EF) Late Finish (LF) Total Slack (LS-ES) A R&D study 4 - B
Jobs | Duration (months) | Predecessors | Early Start (ES) | Late Start (LS) | Early Finish (EF) | Late Finish (LF) | Total Slack (LS-ES) |
A R&D study | 4 | - | |||||
B product design | 5 | A | |||||
C consumer testing | 4 | A | |||||
D market | 2 | B,C |
The project above is scheduled in months. There is a pentalty of $10,000 for every month over 9 months to completion. Fill in the table and Identify the least cost schedule in excel and show your work.
COSTS FOR REDUCING TIMES INCLUDE:
reducing activity B from 5 months to 4 months costs an additional $6000
activity B can be reduced from 5 months to 3 months for $13000 total
activity C can be reduced from 4 months to 3 months at a cost of $3000
activity D can be reduced from 2 months to 1 month at a cost of $9000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started