Jobs Duration (months) Predecessors Early Start (ES) Late Start (LS) Early Finish (EF) Late Finish (LF) Total Slack (LS-ES) A R&D study 4 - B

Jobs Duration (months) Predecessors Early Start (ES) Late Start (LS) Early Finish (EF) Late Finish (LF) Total Slack (LS-ES)
A R&D study 4 -
B product design 5 A
C consumer testing 4 A
D market 2 B,C

The project above is scheduled in months. There is a pentalty of $10,000 for every month over 9 months to completion. Fill in the table and Identify the least cost schedule in excel and show your work.

COSTS FOR REDUCING TIMES INCLUDE:

reducing activity B from 5 months to 4 months costs an additional $6000

activity B can be reduced from 5 months to 3 months for $13000 total

activity C can be reduced from 4 months to 3 months at a cost of $3000

activity D can be reduced from 2 months to 1 month at a cost of $9000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Managerial Accounting Version 3.0

Authors: Kurt Heisinger, Joe Ben Hoyle

1st Edition

1453399410, 9781453399415

More Books

Students also viewed these Accounting questions

Question

Now I need you to write Force Majeure for this assightment for me

Answered: 1 week ago