Joe contracted to excavate and install a swimming pool in Barney's back yard for $20,000. Halfway through Joe found solid rock just eight feet below

Joe contracted to excavate and install a swimming pool in Barney's back yard for $20,000. Halfway through Joe found solid rock just eight feet below the surface. Joe had not known about the bedrock and digging a hole for a pool out of the rock would naturally increase Joe's costs tremendously. Joe explained this problem to Barney and asked Barney to pay another 5,000 for the job. Barney agreed to this as he was anxious to use the pool because temperatures were already hitting 85 degrees F. Joe finished the pool but Barney refused to pay any more than the original $20,000. In answering the questions below, support your analysis with Joe's best argument as well as Barney's best.

1. Could Joe require Barney to pay the additional $5,000? Articulate answers for both parties' positions (homeowner vs. contractor and vice versa).

2.Assume contractor had not installed any pools in any of the neighbors' yards but is experienced. Discuss whether it is relevant whether contractor had put in pools (below ground level) in the area close to Barney Rubbles property.

Neatly number and space the responses according to my numbered questions.Be specific and thorough. Thank you

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Elements Of Chemical Reaction Engineering

Authors: H. Fogler

6th Edition

013548622X, 978-0135486221

Students also viewed these Law questions