Joeblog imports spectrometers for forensic laboratories and educational institutions. The item s demand fore - casts for the next 6 weeks are 2 5 units,
Joeblog imports spectrometers for forensic laboratories and educational institutions. The items demand fore casts for the next weeks are units, followed by fore casts of units for weeks through The current
onhand inventory is units. The order policy is to produce in lots of The booked customer orders for the item, starting with week are and units. The lead time is weeks.
a Develop an MPS for the spectrometer.
b The marketing department has received further
orders for this item in the following sequence: Order is for units to be delivered in period Order is for units to be delivered in period Order is for units to be delivered in period Order is for units to be delivered in period Order is for units to be delivered in period Order is for units to be delivered in period
Assuming that the prospective MPS you developed in part a does not change, which orders would you be able to accept based on the available to promise ATP
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started