Question

1 Approved Answer

Joe's Pizza orders some key ingredients, including pepperoni, from Italy. Because of this, the lead time is 3 weeks. Joe's uses an average of 150

Joe's Pizza orders some key ingredients, including pepperoni, from Italy.  Because of this, the lead time is 3 weeks.  Joe's uses an average of 150 lbs of pepperoni each week, with a standard deviation of 30 lbs.  Joe uses an order up to the level to manage inventory - his order up to level is S= 750.  Joe is about to place an order and notes that he has 500 lbs of pepperoni in his walk-in refrigerator and 100 lbs of pepperoni on order.  How many pounds of pepperoni does he order?

Step by Step Solution

3.54 Rating (175 Votes )

There are 3 Steps involved in it

Step: 1

Order upto level S 750 Inventory position ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations And Supply Chain Management

Authors: F. Robert Jacobs, Richard Chase

14th Edition

978-0077824921, 78024021, 9780077823344, 007782492X, 77823346, 978-0078024023

More Books

Students also viewed these General Management questions