John is the project manager of the XYZ project. He received a voicemail from his hardware vendor saying that the delivery of the equipment he
John is the project manager of the XYZ project. He received a voicemail from his hardware vendor saying that the delivery of the equipment he has ordered would not arrive on time. He identified a risk response strategy for this risk and has arranged for a local company to lease the needed equipment until it arrives. Which type of risk response is this