John works as a project manager for Certify Inc. During the project execution, he carries out an earned value management on a project and determines
John works as a project manager for Certify Inc. During the project execution, he carries out an earned value management on a project and determines that the CPl is 1.3 and the SPl is 0.77. What do these figures indicate? The project is over-budget and behind schedule. B The project is under-budget and behind schedule. The project is over-budget and ahead of schedule. D The project is under-budget and ahead of schedule