Question

1 Approved Answer

Johnny is a Project Manager at PLC Inc. He is tasked to build two double bedroom apartments a month for the coming twelve months. Each

Johnny is a Project Manager at PLC Inc. He is tasked to build two double bedroom apartments a month for the coming twelve months. Each apartment costs a hundred thousands rands. At the beginning of the tenth month, he has constructed 20 apartments and he has determinded the Cost Performance Index (CPI) to be 0.9091.

What is the actual cost of the project right now?(Round off your answer to the nearestmillionrands)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management And Cost Accounting

Authors: Alnoor Bhimani, Srikant M. Datar, Charles T. Horngren, Madhav V. Rajan

7th Edition

1292232668, 978-1292232669

More Books

Students also viewed these Accounting questions

Question

understand what working means to workers;

Answered: 1 week ago

Question

What is a staffing management plan?

Answered: 1 week ago

Question

1. To generate a discussion on the concept of roles

Answered: 1 week ago