Johnson Cogs wants to set up a line to serve 8 0 8 0 customers per hour. The work elements and their precedence relationships are

Johnson Cogs wants to set up a line to serve 8080 customers per hour. The work elements and their precedence relationships are shown in the following table:
Work Element
Time(sec)
Immediate Predecessor(s)
A
2727
None
B
2525
A
C
3434
A
D
2828
B
E
66
B
F
2020
C
G
1010
C
H
1414
D, E
I
12
F, G
J
26
H, I
Total
202
Suppose that a solution requiring five stations is obtained. What is its efficiency?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these General Management questions