Johnson Cogs wants to set up a line to serve 8 0 8 0 customers per hour. The work elements and their precedence relationships are
Johnson Cogs wants to set up a line to serve customers per hour. The work elements and their precedence relationships are shown in the following table:
Work Element
Timesec
Immediate Predecessors
A
None
B
A
C
A
D
B
E
B
F
C
G
C
H
D E
I
F G
J
H I
Total
Suppose that a solution requiring five stations is obtained. What is its efficiency?