Question

1 Approved Answer

Johnson Electronics manufactures a power supply used in a variety of electronics products, including printers, modems, and routers. The demand for the part is 7,600

Johnson Electronics manufactures a power supply used in a variety of electronics products, including printers, modems, and routers. The demand for the part is 7,600 units per week. The production of the power supply requires six different manufacturing operations, each in sequence and each having the following processing times. The net available time to work is 54 hours per week, using two shifts.

OperationProcessing Time

(seconds)Operation 123Operation 220Operation 326Operation 422Operation 529Operation 624

Required:

1. What is the Takt time, in seconds, for this product?(Round your final answer to the nearest whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting

Authors: Kim Langfield Smith, Helen Thorne, David Alan Smith, Ronald W. Hilton

7th Edition

978-1760421144, 1760421146

Students also viewed these Accounting questions