JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $5,000,000 . JRE2 recognizes revenue upon contract completion. Cost incurred
JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $5,000,000. JRE2 recognizes revenue upon contract completion.
Cost incurred | Estimated Cost to Complete | |||
2020 | $ | 180,000 | $ | 1,620,000 |
2021 | 1,600,000 | 500,000 | ||
2022 | 450,000 | 0 |
Required: What would be reported as gross profit (loss) in 2020? (If loss, enter as negative).