just need answers 1) A planning document indicating the type of human resources needed and the amount of time they are required for a project

just need answers

1) A planning document indicating the type of human resources needed and the amount of time they are required for a project is called a(n):

Group of answer choices

HR Management Plan

Project HR Requirements

Staffing Info Plan

Project Organization Chart

2) A hierarchical chart that demonstrates the structure of the project and how the areas of responsibility interrelate is called a(n)

Group of answer choices

Staffing Info Plan

Project HR Requirements

Project Organization Chart

HR Management Plan

3) A planning tool used to clarify the planned involvement of people within the team is called a

Group of answer choices

Responsibility Assignment Matrix

People Involvement Matrix

Responsibility Charter

Project Scope Statement

4) In a RACI chart, the A is short form for

Group of answer choices

Action

Ability

Activity

Accountable

5) A numerical value used to make objective quality measurements is a

Group of answer choices

Tolerance

Standard

Metric

Quality measure

6) A planning document that describes the quality standards to be achieved for the project is a

Group of answer choices

Quality Charter

Quality Achievement Standard

Quality Management Plan

Quality Standards Definition

7) The actions to be performed in the event that the defined risk occurs is a(n):

Group of answer choices

Risk response plan

Project risk plan

Contingency plan

Action plan

8) A potential situation that could cause a negative or positive impact to the project is known as a(n)

Group of answer choices

Problem

Risk

Activity

Issue

9) On a project team, human resources are always acquired from inside the organization.

Group of answer choices

True

False

10) When planning for the project team, the Project Management creates a document known as the Project HR Requirements.

Group of answer choices

True

False

11) The Project Roles and Responsibilities document is a hierarchical document that displays the reporting relationships on the project team.

Group of answer choices

True

False

12) A key theme of quality management is that inspection is the best defense against quality defects.

Group of answer choices

True

False

13) Project quality tends to be closely associated with the scope of a project.

Group of answer choices

True

False

14) Tolerance is a numerical value used to make objective quality measurements.

Group of answer choices

True

False

15) Normally, it is the sole responsibility of the Project Manager to identify the majority of project risks.

Group of answer choices

True

False

16) Risks may be assessed both quantitatively and qualitatively.

Group of answer choices

True

False

17) The "I" in a RACI Chart stands for "Investigate."

Group of answer choices

True

False

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Research Methods For Business Students

Authors: Mark Saunders, Philip Lewis, Adrian Thornhill

4th Edition

0273701487, 9780273701484

More Books

Students also viewed these General Management questions

Question

Relax your shoulders

Answered: 1 week ago

Question

Keep your head straight on your shoulders

Answered: 1 week ago