Question

1 Approved Answer

- Just refer to the tables - Draw an AON diagram - Find ES, EF, LS, LF - Find critical Paths and activities 27. In

image text in transcribed- Just refer to the tables - Draw an AON diagram - Find ES, EF, LS, LF - Find critical Paths and activities

27. In the following table, task durations are given in weeks. The estimates were made at the 95 percent level (see Section 5.2, Calculating Probabilistic Activity Times subsection). a. Find the expected time and variance for each task. b. Draw the network (either AOA or AON ) and find the critical path and time. c. Find the probability that the critical path will be completed in 23 weeks. d. Find the probability that the other main paths will be completed in 23 weeks. e. What is the probability that the entire network will be completed in 23 weeks

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render

11th edition

9780132921145, 132921146, 978-0133408010

More Books

Students also viewed these General Management questions