Kathy Patterson is facing a multiple IRRs problem with an upcoming project with the following anticipated cashflows: Time 0 1 2 Cashflows -1.6 10 -10
Kathy Patterson is facing a multiple IRRs problem with an upcoming project with the following anticipated cashflows:
Time | 0 | 1 | 2 |
Cashflows | -1.6 | 10 | -10 |
The NPV is zero when the discount rate is
a.25%
b. 25% and 600%
c. 25% and 400%
Step by Step Solution
There are 3 Steps involved in it
Step: 1