Kaymer Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations:
Kaymer Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations:
- Materials purchased on account, $23,870.
- Materials requisitioned and factory labor used:
Job Materials Factory Labor 301 $2,420 $2,510 302 2,950 3,390 303 1,960 1,660 304 6,630 6,220 305 4,210 4,740 306 3,070 3,010 For general factory use 820 3,710 - Factory overhead costs incurred on account, $4,620.
- Depreciation of factory machinery and equipment, $1,780.
- The factory overhead rate is $65 per machine hour. Machine hours used:
Job Machine Hours 301 35 302 45 303 39 304 69 305 18 306 35 Total 241 - Jobs completed: 301, 302, 303, and 305.
- Jobs were shipped and customers were billed as follows: Job 301, $8,650; Job 302, $11,120; Job 303, $17,850.
Required:
1. Journalize the entries to record the summarized operations. If an amount box does not require an entry, leave it blank.
Entries | Description | Debit | Credit |
---|---|---|---|
a. | Accounts PayableFactory OverheadFinished GoodsMaterialsWork in Process | fill in the blank 2 | fill in the blank 3 |
Accounts PayableFactory OverheadFinished GoodsMaterialsWork in Process | fill in the blank 5 | fill in the blank 6 | |
b. | Accounts PayableCost of Goods SoldMaterialsWages PayableWork in Process | fill in the blank 8 | fill in the blank 9 |
Accounts PayableAccounts ReceivableFactory OverheadMaterialsWages Payable | fill in the blank 11 | fill in the blank 12 | |
Accounts PayableAccounts ReceivableFactory OverheadMaterialsWork in Process | fill in the blank 14 | fill in the blank 15 | |
Accounts PayableCost of Goods SoldFactory OverheadWork in ProcessWages Payable | fill in the blank 17 | fill in the blank 18 | |
c. | Accounts PayableCost of Goods SoldFactory OverheadMaterialsWork in Process | fill in the blank 20 | fill in the blank 21 |
Accounts PayableCost of Goods SoldFactory OverheadMaterialsWork in Process | fill in the blank 23 | fill in the blank 24 | |
d. | Accounts PayableAccumulated Depreciation-Machinery and EquipmentCost of Goods SoldFactory OverheadWork in Process | fill in the blank 26 | fill in the blank 27 |
Accounts PayableAccumulated Depreciation-Machinery and EquipmentCost of Goods SoldFactory OverheadWork in Process | fill in the blank 29 | fill in the blank 30 | |
e. | Accounts PayableAccounts ReceivableFactory OverheadFinished GoodsWork in Process | fill in the blank 32 | fill in the blank 33 |
Accounts PayableFactory OverheadFinished GoodsMaterialsWork in Process | fill in the blank 35 | fill in the blank 36 | |
f. | Accounts PayableAccounts ReceivableFactory OverheadFinished GoodsWork in Process | fill in the blank 38 | fill in the blank 39 |
Accounts PayableFactory OverheadFinished GoodsMaterialsWork in Process | fill in the blank 41 | fill in the blank 42 | |
g. | Accounts ReceivableFactory OverheadFinished GoodsSalesWork in Process | fill in the blank 44 | fill in the blank 45 |
Accounts ReceivableFactory OverheadFinished GoodsSalesWork in Process | fill in the blank 47 | fill in the blank 48 | |
Accounts PayableCost of Goods SoldFactory OverheadFinished GoodsWork in Process | fill in the blank 50 | fill in the blank 51 | |
Accounts PayableCost of Goods SoldFactory OverheadFinished GoodsWork in Process | fill in the blank 53 | fill in the blank 54 |
2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.
Work in Process | |||
---|---|---|---|
(a)(b)(c)(d)(f)(g) | fill in the blank 56 | (a)(b)(c)(d)(e)(f)(g) | fill in the blank 58 |
(a)(c)(d)(e)(f)(g) | fill in the blank 60 | ||
Bal. | fill in the blank 61 |
Finished Goods | |||
---|---|---|---|
(a)(b)(c)(d)(e)(f)(g) | fill in the blank 63 | (a)(b)(c)(d)(e)(f)(g) | fill in the blank 65 |
Bal. | fill in the blank 66 |
3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.
Kaymer Industries Inc. Schedule of Unfinished Jobs | ||||||||
---|---|---|---|---|---|---|---|---|
Job | Direct Materials | Direct Labor | Factory Overhead | Total | ||||
No. 301No. 302No. 303No. 304No. 305 | $fill in the blank 68 | $fill in the blank 69 | $fill in the blank 70 | $fill in the blank 71 | ||||
No. 302No. 303No. 304No. 305No. 306 | fill in the blank 73 | fill in the blank 74 | fill in the blank 75 | fill in the blank 76 | ||||
Balance of Work in Process, January 30 | $fill in the blank 77 |
4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.
Kaymer Industries Inc. Schedule of Completed Jobs | ||||||||
---|---|---|---|---|---|---|---|---|
Job | Direct Materials | Direct Labor | Factory Overhead | Total | ||||
Finished Goods, January 30 (Job 303)Finished Goods, January 30 (Job 305)Finished Goods, January 30 (Job 306) | $fill in the blank 79 | $fill in the blank 80 | $fill in the blank 81 | $fill in the blank 82 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started