Question
Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several
Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:
Activity | Optimistic time (a) | Most likely time (m) | Pessimistic time (b) | Immediate predecessors |
A | 1 | 4 | 7 | - |
B | 2 | 6 | 10 | - |
C | 3 | 4 | 5 | B |
D | 6 | 13 | 14 | A |
E | 3 | 6 | 9 | A, C |
F | 6 | 8 | 16 | B |
G | 2 | 5 | 8 | E, F |
- Draw the AON networks for these activities.
- Filling out following table by calculating the expected time and variance for activities E and G.
Activity | Expected time | Variance |
A | 4 | 1 |
B | 6 | 1.77 |
C | 4 | 0.11 |
D | 12 | 1.77 |
E | 6 | 1 |
F | 9 | 2.77 |
G | 5 | 1 |
- Using the expected time of each activity calculated in part (b) as the duration of the activity, determine the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), and slack for each activity. Fill out the table provided below with your findings.
Activity | ES | EF | LS | LF | Slack time |
A | 0 | 4 | |||
B | 0 | 6 | |||
C | |||||
D | |||||
E | |||||
F | |||||
G | 16 | 21 | 16 | 21 | 0 |
- Determine the total project completion time and the critical path or paths for the project.
The total project completion time is 37.5 days.
- Compute the total project variance and project standard deviation.
The project variance is 5.555555556and the project standard deviation is 2.357022604.
- What is the probability that the project due date is between 18 and 20 days?
The probability for the project due date to be between 18 and 20 days is 0.328626759.
- What is the due date that yield a 58% chance of completion?
The due date with a yield of 58% is 21.1575362.
- What is the probability of completing Activity E by day 18?
- Consider the path B-F-G. What is the probability that this path will exceed the expected project duration?
- Assume there is a delay of 2 days on the expected time used in part (c) for activity F. How does this delay affect the project completion time? Now assume instead that there is a speed-up of 2 day on the expected time used in part (c) for activity F. How does this speed-up affect the project completion time?
- What happens to the slack time of activity F if the expected time of Activity C is shortened by 1 day? Explain your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started