Keller Company has a materials price standard of $2.00 per pound. The materials were purchased at $2.20 a pound. The actual quantity of materials used
Keller Company has a materials price standard of $2.00 per pound. The materials were purchased at $2.20 a pound. The actual quantity of materials used was 3,000 pounds, although the standard quantity allowed for the output was 2,700 pounds Keller Company's materials quantity variance is $600 U. $600 F. $660 F $660 U