Question
Khozas Manufacturing makes calculators for the local retail markets. They have received an order of 4500 calculators. The order is due for delivery on week
Khozas Manufacturing makes calculators for the local retail markets. They have received an order of 4500 calculators. The order is due for delivery on week 5. Each calculator consists of a cover, process chip and keypad. The cover is made up of a display unit and 2 battery housings. The cover is made by the firm and takes 2 weeks to produce. The process chip and keypads are ordered and the lead time is three weeks. Final assembly requires 1 weeks.
There are scheduled receipts as follows:
Process chips 450 (week 1) 900 (week 3) 450 (batch size)
Keypad 480 (week 1) 360 (week2). Batch size = 120
Draw an assembly Time Chart
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started