Kiner, Inc. began work in 2010 on a contract for $8,400,000. Other data are as follows: 2010 2011 Costs incurred to date $3,600,000 $5,600,000 Estimated
Kiner, Inc. began work in 2010 on a contract for $8,400,000. Other data are as follows:
2010 2011
Costs incurred to date $3,600,000 $5,600,000
Estimated costs to complete 2,400,000
Billings to date 2,800,000 8,400,000
Collections to date 2,000,000 7,200,000
If Kiner uses the completed-contract method, the gross profit to be recognized in 2011 is
a. $1,360,000. | ||
b. $2,800,000. | ||
c. $1,400,000. | ||
d. $5,600,000 |