KL Construction Limited (KL) has been contracted to build a new pavilion.The contract price is $120,000.At balance date the pavilion is 50 per cent complete.In

KL Construction Limited (KL) has been contracted to build a new pavilion.The contract price is $120,000.At balance date the pavilion is 50 per cent complete.In terms of the contract, KL has received two progress payments totaling $45,000 by 31 March 2015, which is its balance date. In terms of the contract, on 1 April 2015 KL also submitted the next progress payment invoice for $13,000, and it received this cash on 10 April 2015.

Which of the following statements is correct in terms of the income from the contract?

Select one:

a.If KL reported on an accrual basis: $58,000.

b.If KL reported on an accrual basis: $65,000

c.If KL reported on a cash basis: $55,000

d.If KL reported on an accrual basis: $60,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Financial Accounting

Authors: Fred Phillips, Robert Libby, Patricia A Libby

3rd Edition

0073527106, 9780073527109

More Books

Students also viewed these Accounting questions

Question

How flying airoplane?

Answered: 1 week ago