Question
KL Construction Limited (KL) has been contracted to build a new pavilion.The contract price is $120,000.At balance date the pavilion is 50 per cent complete.In
KL Construction Limited (KL) has been contracted to build a new pavilion.The contract price is $120,000.At balance date the pavilion is 50 per cent complete.In terms of the contract, KL has received two progress payments totaling $45,000 by 31 March 2015, which is its balance date. In terms of the contract, on 1 April 2015 KL also submitted the next progress payment invoice for $13,000, and it received this cash on 10 April 2015.
Which of the following statements is correct in terms of the income from the contract?
Select one:
a.If KL reported on an accrual basis: $58,000.
b.If KL reported on an accrual basis: $65,000
c.If KL reported on a cash basis: $55,000
d.If KL reported on an accrual basis: $60,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started