Knowledge Assessment Matching Match the term in column 1 to its description in column 2. Column 1 Column 2 1. critical path a. the amount
Knowledge Assessment
Matching
Match the term in column 1 to its description in column 2.
Column 1 | Column 2 |
1. critical path | a. the amount of time a task can be delayed before it will delay another task |
2. free slack | b. a restriction that controls the start or finish date of a task |
3. split | c. the condition of a resource when the total work of its task assignments is exactly equal to that resource's work capacity |
4. underallocated | d. the amount of time a task can be delayed without delaying the project completion date |
5. recurring task | e. the series of tasks whose scheduling directly affects the project's finish date |
6. fixed units | f. a restriction that forces a task to begin or end on a certain date, preventing the rescheduling of a task |
7. constraint | g. an interruption in a task |
8. fully allocated | h. the condition of a resource when the work assigned to a resource is less than the resource's maximum capacity |
9. inflexible constraint | i. a task that is repeated at specific intervals |
10. total slack | j. a task type in which the units value does not automatically change |
True/False
Circle T if the statement is true or F if the statement is false.
T | F | 1. It is always best to enter a start or finish date for every task. |
T | F | 3. By default, critical path tasks are shown in red on the Detail Gantt view. |
T | F | 3. It is never acceptable to have an overallocated resource. |
T | F | 4. It is not possible to split a task over a weekend. |
T | F | 5. Effortdriven scheduling and task types both affect all resources in the same way. |
T | F | 6. You cannot change the task type for a summary task. |
T | F | 7. You can use a task calendar to schedule a task that will occur during working time that is not available on the project calendar. |
T | F | 8. It is acceptable to have a resource group named Unassigned. |
T | F | 9. It is not possible to set a specific time of day for a recurring task. |
T | F | 10. You can split a task only three times. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started