Knowledge Assessment Matching Match the term in column 1 to its description in column 2. Column 1 Column 2 1. critical path a. the amount

Knowledge Assessment

Matching

Match the term in column 1 to its description in column 2.

Column 1

Column 2

1. critical path

a. the amount of time a task can be delayed before it will delay another task

2. free slack

b. a restriction that controls the start or finish date of a task

3. split

c. the condition of a resource when the total work of its task assignments is exactly equal to that resource's work capacity

4. underallocated

d. the amount of time a task can be delayed without delaying the project completion date

5. recurring task

e. the series of tasks whose scheduling directly affects the project's finish date

6. fixed units

f. a restriction that forces a task to begin or end on a certain date, preventing the rescheduling of a task

7. constraint

g. an interruption in a task

8. fully allocated

h. the condition of a resource when the work assigned to a resource is less than the resource's maximum capacity

9. inflexible constraint

i. a task that is repeated at specific intervals

10. total slack

j. a task type in which the units value does not automatically change

True/False

Circle T if the statement is true or F if the statement is false.

T

F

1. It is always best to enter a start or finish date for every task.

T

F

3. By default, critical path tasks are shown in red on the Detail Gantt view.

T

F

3. It is never acceptable to have an overallocated resource.

T

F

4. It is not possible to split a task over a weekend.

T

F

5. Effortdriven scheduling and task types both affect all resources in the same way.

T

F

6. You cannot change the task type for a summary task.

T

F

7. You can use a task calendar to schedule a task that will occur during working time that is not available on the project calendar.

T

F

8. It is acceptable to have a resource group named Unassigned.

T

F

9. It is not possible to set a specific time of day for a recurring task.

T

F

10. You can split a task only three times.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Management In The Hospitality Industry

Authors: Clayton W Barrows, Tom Powers

7th Edition

9780471782766

More Books

Students also viewed these General Management questions

Question

Where do the authors work?

Answered: 1 week ago