Question
00
1 Approved Answer
Kokko Company makes a product that is expected to require 2 hours of labor per unit of product. The standard cost of labor is $6.00.
Kokko Company makes a product that is expected to require 2 hours of labor per unit of product. The standard cost of labor is $6.00. Kokko actually used 2.1 hours of labor per unit of product. The actual cost of labor was $6.25 per hour. Kokko made 1100 units of product during the period. Based on this information alone, the labor usage variance is