Konsider the following network diagram: Task 2 (1 day) Task 1 (3 days Task 4 (4 days) Task 3 (Idayu Task 7 (2 days) End
Konsider the following network diagram: Task 2 (1 day) Task 1 (3 days Task 4 (4 days) Task 3 (Idayu Task 7 (2 days) End Task 5 (8 days Task 6 (2 days) The following table shows the budget for this project: Task Task 1 Task 2 Task 3 Task 4 Task 5 Task 6 Task 7 Budget $56,000 $10,000 $48,000 $132,000 $61,000 $51,000 $4,200 1. The fund transfer schedule for the project includes three fund transfers on the following days. Determine the amounts for each transfer and the project account balance at the beginning of each day. Note: this project has no contingency reserves. (9 points). Day Day 1 project start day) Day 5 Day 10 Transfer Amount $ $ $ Project Acct. Bal. $ $ $ 2. The following table shows the list of completed tasks on project at the end of day 5. Calculate the Schedule Performance Index (SPI) and determine whether the project is on schedule, behind schedule or ahead of schedule. (6 points) Task Task 1 Task 5 Actual Cost $62,035 $60,480 $59,260 Task 3
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started